Business Continuity Testing

As per recommended practices ITP recently performed a proactive Disaster Recovery / Business Continuity test for one of our Legal Services Clients.

We were succesfully able to verify that they could work in the event of a datacentre failure . We tested:

  1. the speed of spinning up the redundant protected servers in the cloud
  2. the dissemination of connection details to the test users located at their homes
  3. the ability/speed of the users to connect to the alternate DR environment independently
  4. the usability and responsiveness of critical line of business application and processes

ITP were able to implement additional procedures for processes that needed faster responses and update end user manuals that will be kept with off site pc’s.

The end user was very pleased with the results.